Tender for Gozo Wastewater Treatment Plant Upgrade
Malta’s Water Services Corporation (WSC) has launched an EU co-funded public tender for the design, construction, testing and commissioning of a major upgrade to the Gozo Wastewater Treatment Plant.
Published on 13 November 2026, the procurement (WSC/T/092/2026) has an estimated value of €25,795,000 excluding VAT and is an opportunity for contractors specialising in wastewater infrastructure, treatment technology and water reclamation.
The project is intended to provide capacity and resilience through at least 2040. The existing plant, designed to treat 6,000 cubic metres of wastewater daily, will be supplemented by a new 8,000 m³/day treatment facility, increasing overall treatment capacity to 14,000 m³/day. A new reclamation plant will also produce an additional 4,000 m³/day of ‘New Water’ for reuse.
Works will be delivered in two phases: a new wastewater treatment plant using membrane bioreactor (MBR) technology, followed by a water reclamation facility using reverse osmosis (RO). The successful contractor will undertake the associated civil, mechanical and electrical works while the existing facilities continue operating. The FIDIC-based contract provides for a 140-week completion period.
The tender sets substantial financial and technical eligibility thresholds. Bidders must demonstrate average annual turnover of at least €19 million over the seven consecutive years 2019–2025, supported by the prescribed financial documentation, together with access to a bank credit facility or available financing of at least €8.5 million.
The MBR supplier must provide evidence at least four municipal wastewater treatment MBR plants with capacities of 8,000 m³/day or more, as well as two MBR projects treating high-conductivity wastewater. The RO supplier must demonstrate at least two reverse-osmosis plants with capacities exceeding 4,000 m³/day. These references must relate to plants commissioned during 2017–2026. Participation through joint ventures, subcontractors and reliance on other entities is allowed, subject to the tender’s supporting-document requirements.
The award will not be made on the basis of construction price alone. Among administratively and technically compliant tenders, WSC will select the offer with the lowest calculated total specific treatment cost per cubic metre, taking account of both annualised capital costs (weighted at 35%) and running costs (weighted at 65%) for wastewater treatment and water reclamation. Energy and chemical consumption will therefore be material to bid competitiveness.
Tenderers should also assess the contractual risk allocation. The performance security is initially 10%, reducing to 5% in accordance with the tender provisions; the defects notification period is two years. Delay damages are specified at €5,000 per calendar day for the first 30 days and €20,000 thereafter, subject to a maximum of 20% of the final contract price.
An initial clarification meeting and site visit is scheduled for 30 November 2026, with a further clarification meeting on 12 January 2027. Requests for additional information must be submitted by 16 January 2027. The deadline for electronic submission of tenders is 26 February 2027 at 9:30 a.m. (Malta time). Prospective attendees must register at least 48 hours before the relevant clarification meeting or site visit.
For international engineering and infrastructure contractors, early assessment of eligibility, technology partners, whole-life cost assumptions and the FIDIC contractual conditions will be essential to preparing a compliant and competitive bid.
Our public procurement team can assist interested bidders with consortium and reliance structures, eligibility and selection requirements, preparation of the technical and financial submissions, and the wider contractual and regulatory aspects of the tender.